!!OT HITCH WEEK - Overtime Hitch Week
!!Time Rule Overview
This time rule uses the HITCH time rule helper to determine the start of the week. 

The value in this time rule represents the number of days before the hitch date that will be used to determine the start of the week.

A client could use OT WORK WEEK and WK START OFF DAY instead of HITCH AND OT HITCH WEEK as they behave in similar manners. 

!!Requirements / Features
*The time rule’s role is to determine the start of the week and hitch start date for OT HITCH WEEK and OT CONSC NO SCH  time rules.
*Time Rule Type Code:  OT HITCH WEEK

!!Additional Info 
Frequency  
*predefined as ‘Every Day’

If the start of the week is determined, it will calculate the total time worked in the week until the current day, and compare with the qualifying band to determine if the time rule will be applied or not

If the applied time code set is defined, the rule will apply from the start of the week to the current date and the time code that it is applied should be included in the time code set.

!!Implementation
The time rule should be set up in [IDWR] as shown below. See [Time Rule Improvements|TIME_RULE_IMPROVEMENTS] for additional information regarding [IDWR].

||Band||From||To||Value||Day||Time Code||Premium||Action||Target Time Code Set||Apply Time Code Set
|min hours worked to qualify|No|No|min days before hitch start|Yes|Yes|Yes|Add/Replace|Required|Allowed

 